Key facts
The Swiss Armed Forces need real estate to fulfil their training and operational mission. This includes barracks, military airfields and military training areas, for example. These properties are recorded in the real estate portfolio of armasuisse Real Estate (ar Immo), which had a value as new of CHF 28.4 billion at the end of 2025. Of this, CHF 23.9 billion is in the core portfolio and is therefore in longer-term use. The current geopolitical situation is leading to a realignment of the Armed Forces, which is also changing their real estate portfolio. The stationing concept originally envisaged reducing the core portfolio to CHF 20 billion. In 2022, however, this was reversed in favour of an expansion to up to CHF 30 billion.
The Swiss Federal Audit Office (SFAO) examined whether ar Immo steers its portfolio with suitable instruments and, on the basis of adequate requirements, ensures that projects are carried out economically.
The audit identified several areas requiring action, some of them already known: unclear user requirements, a missing strategy, insufficient steering, a backlog of repairs and a lack of standardisation. As a result, ar Immo can perform its tasks only to a limited extent. The Real Estate Board must therefore take fundamental decisions on the direction to be taken.
21,600
objects in total including 6,070 buildings
10,000
objects are in the core portfolio and in longerterm use
28.4bn
value as new
≤ 6bn
planned expansion of the core portfolio
Main conclusions
-
Expansion poses a major challenge
The planned expansion of the portfolio requires funding. However, as the necessary bases are lacking, ar Immo cannot quantify how much. It is unclear whether and how the entire requirement can be met.
-
Timely decisions of principle by the Real Estate Board are lacking
The realignment of the Armed Forces is exacerbating differences over organisation and over priorities in the real estate area. ar Immo depends on clear steering.
-
Use and usefulness of key figures partly unclear
The incorrectly maintained indicators in ar Immo’s internal portfolio controlling report are not reliable steering values. Responsibilities and deadlines are also lacking.
-
User requirements are unclear
The development of the portfolio is based on various Armed Forces planning documents. These are not up to date, which means that ar Immo cannot set concrete goals for real estate planning.
-
Standardised construction methods are not yet being used
Standardised construction has long been an objective in the Armed Forces domain. However, differing goals and differences in basic understanding have so far prevented this efficiency gain from being realised.