Key facts
In response to the threat of a winter electricity shortage, the Confederation gradually established a winter reserve from 2022 onwards. To secure this electricity reserve between 2030 and 2045, the Confederation plans to provide generation capacity from four reserve power plants at a cost of CHF 2.3 billion. Parliament is expected to consider the matter during the 2026 autumn session. The winter reserve is financed by consumers through a surcharge on electricity tariffs.
The Swiss Federal Audit Office (SFAO) conducted its audit at the Swiss Federal Office of Energy (SFOE), the Federal Electricity Commission (ElCom) and Swissgrid. It assessed the decision-making process for determining the need for the electricity reserve, the economic efficiency of the selection and sizing of the individual reserve types, and the procurement process for the new reserve power plants. Overall, the procurement of reserve capacity was economically efficient. However, significant savings potential remained untapped in the selection and sizing of the individual reserve types.
500MW
of reserve capacity required (minimum capacity recommended by ElCom)
583MW
of capacity from reserve power plants from around 2030 onwards
CHF 2,3
billion budget for reserve power plants
CHF 220
million in potential savings from emergency generators and avoiding oversizing
Main conclusions
-
Reserve requirement level determined in an understandable way
The decision-making process for determining the level of required capacity is understandable. However, determining the reserve requirement remains a matter of political judgement, with significant uncertainties involved.
-
Potential savings of CHF 220 million
Emergency generators were not taken into account as a reserve type, although at least some of their capacity could be used cost-effectively for the electricity reserve. In addition, oversizing by 83MW has resulted in unnecessary costs.
-
Key role for renewable energy
An expansion of renewable energy in line with targets would significantly reduce the reserve requirement.
-
Savings at the expense of higher risks
The direct award and subsequent contract negotiations resulted in more favourable terms, but also led to increased risk exposure for the Confederation, with potential cost implications.
-
Lack of transparency regarding contractual risks and costs
A systematic assessment of contractual risks is necessary to allow the Confederation to ensure that these risks are continuously reduced over the entire project duration of the reserve power plants.
-
Contract transfer before commissioning entails risks
Transferring responsibility from the SFOE to Swissgrid during the construction phase of the reserve power plants could result in information loss and project delays due to a lack of expertise.